Project G-0612
Larimer Yard Lofts
Five stories of wood frame over a concrete podium in RiNo, handed over eleven days early in 2024.
G-0612
118 apartments, eleven days early
Five stories of wood frame over a concrete podium, built for Northline Residential under a CM-at-risk contract.
The brief
Northline Residential bought a one-acre rail yard parcel on Larimer Street with a construction loan that priced every month of delay. They needed 118 units leasing by spring 2024, a ground-floor coffee tenant open on day one and a podium that would satisfy a skeptical lender's inspector.
What we did
- Podium in 11 weeks. Post-tensioned concrete poured with our own pump and crane, two weeks ahead of the baseline.
- Panelized framing. Wall panels built off site and set floor by floor, cutting framing time by 30%.
- Inspections booked ahead. Every city inspection on the calendar three weeks out, posted in the Friday report.
- Leasing from floor two. Phased temporary certificates let Northline lease the lower floors while the roof was finished.



Job G-0612Larimer Yard
- Owner
- Northline Residential
- Type
- Multifamily, 5 over 1
- Size
- 142,000 sq ft · 118 units
- Contract
- $31.4M · CM at risk
- Permit no.
- 2022-COM-00877
- Superintendent
- Hank Morrow
- Date on sign
- Mar 14, 2024
- Handed over
- Mar 3, 2024
11 days early · 3 change orders
Request this referenceThey painted March 14 on the fence sign the week they mobilized. We cut the ribbon on March 3.
Andrea Feld · Northline Residential